Rainier’s school bond options: $6 million to $23 million, roof first

The school board adopted a facilities plan with nine possible bond packages for May 2027. Every one starts with a $6.5 million roof, and $6.1 million in state matching money depends on voters saying yes.

The Rainier School Board has adopted a long-range facilities plan that puts prices on what it would take to repair a campus built in 1978, and the first number on every version of the list is the same: $6.5 million for a new roof.

The board approved the plan Nov. 9, according to a district announcement posted the next day. The 14-page plan, prepared by the Portland office of DLR Group and dated Nov. 5, lays out nine possible bond packages for a May 2027 election, with requests to voters ranging from $6.25 million to $22.95 million.

Adopting the plan also makes Rainier eligible to apply for about $6.1 million from the state’s Oregon School Capital Improvement Matching program. The money comes only if voters approve a bond of at least that amount. The district expects to learn in December whether it has been awarded the grant, the announcement says.

The Tribune previewed the vote on Nov. 9 and reported in October that the district is planning its first bond in nearly 50 years. The board has not yet voted to put a measure on the ballot.

What the Committee Ranked First

A Facilities Advisory Committee of seven staff members and 14 community members met five times between May 28 and Nov. 4, toured the buildings, and scored 16 kinds of work, according to the plan. The lowest score marked the highest priority. The top five:

RankWorkScore
1Roof replacement10
2Fire sprinklers22
3Heating and cooling23
4Accessibility improvements26
5Electrical service upgrades42

Pool upgrades ranked 12th. New entries for the elementary, middle, and high schools ranked 13th. Sports fields and lighting ranked last.

Nine Packages, One Constant

Every scenario in the plan starts with the roof and subtracts the $6.1 million state match from the total. Three of the nine:

Bond requestTotal workWhat it covers
$6.25 million$12.35 millionRoof, fire sprinklers, accessibility, reorganizing the middle and high school areas, new entries
$14.1 million$20.2 millionRoof, heating and cooling, windows, restrooms, fire sprinklers, accessibility, new entries, wall changes, electrical, parking lot
$22.95 million$29.05 millionRoof, pool upgrades, flooring, windows, track and field, restrooms, fire sprinklers, gym heating and cooling, accessibility, reorganizing the middle and high school areas, new entries, ceilings, electrical, parking lot

The plan also lists a pool-to-gym conversion at $2.9 million and track and field work at $2.7 million as projects that could be paid for with outside grants instead of the bond.

What It Could Cost Taxpayers

The plan includes estimates from the district’s bond adviser, Piper Sandler, shared with the committee Nov. 4, of how much a given tax rate would raise in a May 2027 election:

Rate per $1,000 assessed value20-year bond30-year bond
$1.00$14.63 million$18.23 million
$1.25$18.29 million$22.77 million
$1.50$21.94 million$27.32 million

At $1.00 per $1,000, the owner of a home assessed at $300,000 would pay $300 a year; at $1.50, $450. Those are the Tribune’s calculations from the rates in the plan. The plan does not match a tax rate to each of the nine packages, and the board has not chosen one.

The Buildings

Rainier voters approved a $7 million bond nearly 50 years ago to build the campus on a 160-acre site, the plan says. Hudson Park Elementary, the junior-senior high classroom building, the shop, and the 83,876-square-foot commons were all completed in 1978. The plan calls for removing portable and modular buildings, added between 1995 and 2004, as “beyond their intended service life.”

The committee’s list of needs also includes security cameras and controlled doors, replacement windows, a new fire alarm and sprinkler system, new servers and technology space, and updated restrooms. For the closed pool, the plan lists upgrading the pool and its mechanical equipment, and converting the main pool to an auxiliary gym and the diving pool to a weight room.

No building on campus is registered as historic, and the district does not plan to add buildings, according to the plan.

What Happens Next

The state’s decision on the matching grant is expected in December. A bond would need a separate vote of the seven-member board, chaired by Eric Schimmel, to reach the May 2027 ballot. The district office is at 503-556-3777.