Scappoose bond committee favors remodeling the middle school; vote targeted for 2027

Options ran from $65 million to $97 million. A state sheet still lists a $6.1 million match for a 2026 Scappoose bond that never went to voters.

The committee planning Scappoose’s next school bond is leaning toward remodeling and adding on to the existing middle school instead of building a new one, and toward a measure sized to keep the district’s bond tax rate where it is. The target is the November 2027 ballot.

The Community Bond Advisory Committee reached that position at its Nov. 3 meeting, consultants from Wenaha Group told the School Board on Nov. 9, according to the board’s minutes.

Five Options, $65 Million to $97 Million

The committee looked at five options for a middle school: three at the current middle school site, one on the high school campus, and one on a new site. Preliminary estimates ran from about $65 million for new construction at the existing site to about $97 million for a new site. The estimates “are still being refined and do not include all potential demolition or gym-related costs,” the minutes say.

After small-group discussion and what the minutes call a consensus exercise, members supported the remodel-and-addition option, “which is designed to maintain the current bond tax rate.” They also favored keeping the school where it is, preserving gym space for community and after-school programs, and using any leftover bond money on deferred maintenance at other buildings.

The committee asked for more detail on the existing building’s square footage and on the cost assumptions. It takes up construction approaches and costs in December.

The Timeline

  • March 2027: draft recommendation.
  • April and May 2027: community feedback.
  • June 2027: final recommendation to the board.
  • November 2027: target election.

Those dates are from the board’s Oct. 12 minutes.

A State Match Tied to a Measure That Never Ran

The district’s committee page says the group was formed to “explore a possible 2026 school bond.” No Scappoose school bond appeared on the Nov. 3 ballot.

The state still has one on its books. An Oregon Department of Education sheet dated Nov. 6 and titled as the November 2026 results of the Oregon School Capital Improvement Matching program lists Scappoose with a local bond of $108,904,000 and a state matching grant of $6,126,000. The file’s properties show it was built from a matching database “as of 7.15.26.”

The program commits state money to districts before an election and pays it only if voters approve the local bond. The state’s documents do not say whether Scappoose’s commitment carries over to a 2027 measure.

Scappoose voters last saw a district bond in November 2023. Measure 5-296 asked for up to $110 million, mainly to replace the middle school, which the ballot summary described as 92 years old.

The School Board meets next on Monday, Dec. 14, at 6 p.m.