Why a salmon ruling is costing Columbia River PUD $1.25 million a year

A federal court’s dam spill order pushed BPA to seek a 6.3 percent increase. Columbia River PUD says it will absorb its share rather than raise rates, and its 2027 budget meeting is Nov. 17. A Nov. 4 settlement would trim BPA’s number.

Columbia River PUD expects to pay about $1.25 million more a year for wholesale power in each of the next two years because of a federal court order that sends more Columbia and Snake river water over dam spillways instead of through turbines. The utility says it does not plan to raise rates to cover it. Its board takes up the 2027 budget Tuesday, Nov. 17, at 5:30 p.m., the second of two public budget meetings.

How a Salmon Ruling Reaches a St. Helens Power Bill

On Feb. 25, U.S. District Judge Michael Simon ordered more spill at eight federal dams on the lower Columbia and Snake rivers to protect endangered salmon and steelhead, after the federal government withdrew from a 2023 settlement that had paused the long-running lawsuit, OPB reported. Spilled water generates no electricity, so the Bonneville Power Administration, which markets the dams’ power, bought replacement power on the wholesale market “at much higher prices,” the PUD said in an Oct. 28 explainer for customers.

BPA asked in September for a 6.3 percent increase to cover a $250 million shortfall, according to OPB. Columbia River PUD owns no generation and buys all of its power from BPA as a preference customer, per its press kit, so a BPA increase lands directly on its books. The PUD put its share at roughly $1.25 million a year for two years.

“We are not planning to pass those additional costs directly on to our customers through a rate increase,” General Manager Michael J. Sykes said in the release, which says the utility will absorb the hit through “financial management and planning.”

The Number May Shrink

Since the PUD wrote that, the figure has moved. On Nov. 4 conservation groups that challenged the increase announced a settlement under which BPA would collect $212 million instead of $250 million, about $38 million less, and would be more likely to refund money to customers in 2028, Earthjustice said. BPA has to adopt the settlement, with a final rate decision expected in early December. The PUD has not said what the smaller figure means for its $1.25 million estimate.

What the PUD Charges Now

Columbia River PUD serves 20,860 customers across 240 square miles, 18,255 of them residential, with 52 employees, per its press kit. It reports an average residential rate of 9.75 cents per kilowatt-hour in 2025, which it says is 37 percent below the Oregon average and 44 percent below the national average, a saving it values at about $705 per residential customer a year. Clatskanie PUD’s board meets Nov. 18 at 6 p.m.; its website has nothing posted on the BPA increase.

The Nov. 17 budget advisory meeting is where the “absorb it” plan gets its first public test. The notice says the meeting covers the 2027 operating and capital budget.