COLUMBIA COUNTY, Columbia County says it will not be the one borrowing the $13.6 million it needs to match its federal broadband grants. A nonprofit the county created in October will do that, through a federal loan and revenue bonds, with no county guarantee behind it “at this time.” The county also says the nonprofit has no board of directors yet, that its bylaws are still a first draft, and that the county, not the nonprofit, still answers to the federal government if the network is never built.
The answers came from County IT Director Holly Miller in a written reply late on Nov. 7, 15 days after the Tribune sent the county four questions and eight days after the Tribune’s Oct. 30 deadline. The Tribune reported Oct. 27 that the county had won about $16 million in federal Broadband Equity, Access, and Deployment money, pledged about $13.6 million in match, and registered Columbia Community Broadband Corporation at the courthouse address without announcing any of it. That story said the county had not responded. It has now.
What the County Said
Miller confirmed that the Board of Commissioners authorized the corporation and approved its articles of incorporation, and that Board Chair Kellie Jo Smith is the listed incorporator. The corporation’s job is “to finance, construct, own, and operate the broadband network,” she wrote, with “an experienced contracted operator” running it day to day. The county stays the grant recipient and keeps responsibility for meeting the grant’s terms.
The corporation lists 230 Strand St. because that is the courthouse, Miller wrote, and it will “reside” there until it has an office of its own. Its board of directors “has not yet been established,” and the first draft of its bylaws is “currently under development.” Both, along with a subgrant agreement that would move the federal money from the county to the corporation, will come back to the commissioners at public meetings. “Those meeting dates have not yet been identified,” she wrote.
The board acted on Sept. 9 and signed Resolution 30-2026 on Sept. 11, Miller wrote. The resolution approves the state grant agreement, approves forming the corporation, and says the articles and bylaws “shall be approved by the Board prior to their filing.” The articles were filed with the Secretary of State on Oct. 9, per the state business registry. The bylaws, by the county’s account, are not finished.
Who Borrows the Match
The county’s answer on the match is that it will not pay it. “The County will not fund the match; it will pass the grant funding along to CCBC as reimbursable work is completed and approved,” Miller wrote. The corporation plans to apply for a U.S. Department of Agriculture ReConnect loan “when Round 6 of the ReConnect program opens,” repaying it from network revenue after a three-year deferment, and to sell revenue bonds to reach addresses the federal programs will not pay for. Together the two are “planned to total up to the amount of the required match,” she wrote. “No match financing has yet been approved.”
There is no sixth ReConnect round to apply to yet. USDA’s ReConnect page says the agency “is NOT currently accepting applications for processing for this program due to pending guidance and authorization”; the last round closed in May 2024. The head of USDA’s Rural Utilities Service said in April that a sixth round would come “sooner than later” and that the program’s future depended on the Farm Bill, Broadband Breakfast reported. ReConnect’s eligibility rules differ from BEAD’s, Miller noted, so the corporation will have to check which of the grant’s locations qualify.
The resolution the board signed in September says the grants “cover approximately half the amount needed to build the proposed broadband network” and that the county “lacks the resources to fill that gap in funding.” It requires the board to approve any bond issue or other financing before the corporation takes it on, and it says the corporation’s debt “shall never constitute a debt, liability, or general obligation of Columbia County.” Miller’s reply says the same: “The financing plan does not include a county guarantee or other committed County financial support at this time.”
What the County Still Carries
The county does not claim the arrangement makes it risk-free. “Although CCBC, not the County, would be responsible for its borrowing, the County remains responsible for its obligations under the BEAD agreement,” Miller wrote. “If CCBC cannot complete the project or meet the grant requirements, the County could face completion costs, grant repayment, or other contractual consequences.” Because the grant reimburses work after it is done rather than paying up front, she wrote, the county’s repayment risk “is significantly reduced,” not eliminated.
When the corporation’s debt is paid off, the network and everything else the corporation owns transfer to the county automatically, under the resolution. Until then the county holds what the resolution calls a “beneficial interest” and a senior right to step in, cure a default, and take the assets if the corporation fails.
Where the Money Goes
Miller confirmed the award figures the Tribune reported, which follow school district boundaries rather than city limits:
| Project area | BEAD grant | Required match |
|---|---|---|
| Rainier School District | $4,000,000 | $4,053,953 |
| Scappoose School District | $3,000,000 | $4,157,906 |
| Vernonia School District | $2,517,400 | $3,212,953 |
| St. Helens School District (pending) | $6,534,346 | $2,178,115 |
| Total | $16,051,746 | $13,602,927 |
The district areas take in rural communities such as Mist, Birkenfeld, Beaver Homes, Chapman, and Prescott, Miller wrote, but the grants pay for specific eligible addresses, “not service to every address in each district.” The state’s BEAD map shows the district grant areas. The Clatskanie district area went to Starlink, she wrote, though the county network could be extended there later with more money and approvals.
The St. Helens project, the largest of the four, is still not final. It was reassigned to the county in July after another provider walked away, and the federal National Telecommunications and Information Administration has not approved the state’s package containing that reassignment, Miller wrote. The Oregon Broadband Office’s September presentation to the state broadband council lists the county’s 1,058-location re-award among “preliminary awards pending NTIA approval.” Once approved, the state will amend the county’s grant agreement to add it.
What Comes Next
No construction can start until contracts are signed and federal environmental and historic preservation review is complete, according to the state broadband office’s presentation, which says awardees then have four years to finish. The county signed its state contract ahead of a Sept. 18 deadline.
The Tribune asked for the corporation’s articles and bylaws, the signed grant agreement, and the board order authorizing it. Miller did not attach them, writing that under the county’s records policy the Tribune must file a public records request to get copies. The resolution is posted in the county’s orders and resolutions archive; the grant agreement was in the board’s Sept. 9 meeting packet.
The next public steps, by the county’s account, are board votes on the bylaws, a board of directors, and the subgrant agreement, on dates not yet set.