COLUMBIA CITY, Update, Nov. 20: The state parks commission met Nov. 17 and 18. The department’s summary of the meeting lists a “request to approve local government grant recommendations” among the items the commission took up, but it does not name the projects, and the state had not posted the list of awards as of Friday. The Tribune will update this story when it is published.
Columbia City will find out this week whether the state will help pay for a new playground at Harvard Park. The city applied for $100,000 from the Oregon Parks and Recreation Department, and City Administrator Kim Karber told the City Council on Oct. 15 that the project is on the list recommended for approval when the state parks commission meets Wednesday, Nov. 18.
The commission’s business meeting starts at 9:30 a.m. in Newport, according to an Oregon Parks and Recreation Department release. The city expects to be notified after the vote, according to Parks Committee minutes in the council’s Nov. 19 packet.
What the Money Would Buy
The city asked for $100,000 “to use towards playground equipment, parking spots, and adding ADA accessibility,” according to the Parks Committee’s Sept. 8 minutes. Karber told the committee the state grant program has three tiers: $50,000 and under, $50,000 to $100,000, and more than $100,000 up to $1 million. The state completed a technical review of the application, the city made the requested changes and resubmitted it, and a state advisory committee was scheduled to rank the applications in late September or early October.
Harvard Park is a 0.39-acre neighborhood park on Sixth Street between Calvin and Penn streets. It has playground equipment, an open lawn, benches, picnic tables, a drinking fountain, and a restroom, according to the city’s parks page.
In April, Karber and Public Works Superintendent Micah Rogers met with a representative of GameTime about playground equipment. He told them the new playground would not need a much larger footprint than the current one, “since we have a small number of kids playing at once,” and that the city “should be able to do it for under 100,000,” according to the April 14 minutes. Any layout the city picks can be built in purple, he said. The teeter-totter is the only piece of current equipment the city plans to keep.
The Parks Committee put “Harvard Park renovations – playground upgrade, picnic shelter, ADA access improvements” first on its five-year capital plan in February, scheduled for the 2026-27 budget year. The vote was 4-1, according to the Feb. 23 minutes.
Why This Park
Harvard Park has the only public playground in Columbia City, according to the Parks Master Plan the council adopted Feb. 19. The consultants who inspected it wrote that the “play equipment is clearly aging” and that the “park has no ADA access or accommodation.” They found the wood chips under the equipment “not deep enough to provide fall safety attenuation,” noting that 15 inches of engineered wood fiber is the minimum, and called the Japanese barberry hedge “not an appropriate planting near a children’s play area.”
The plan makes replacing the playground “with grant assistance from Oregon Parks and Recreation Department” a city policy and prices the work well above the vendor’s estimate. Its capital list for Harvard Park, with the accessibility work scheduled for 2026-27 and the rest for 2028-29:
| Project | Estimated cost | Plan’s timing |
|---|---|---|
| Play equipment replacement | $203,000 | 2028-29 |
| Small picnic shelter with path | $87,000 | 2028-29 |
| Accessible routes | $26,000 | 2026-27 |
| Accessible bench and picnic table | $8,000 | 2026-27 |
| Shade trees | $6,000 | 2028-29 |
| Total | $330,000 |
The total is the Tribune’s addition of the plan’s figures. The Parks Committee’s own five-year list, approved the same month, put the whole Harvard Park renovation in 2026-27. The city budgeted $90,000 for Harvard Park improvements this fiscal year and had spent none of it through Oct. 31, according to the expense report in the council packet.
The money would come from the state’s Local Government Grant Program, which voters approved and the Oregon Lottery funds. The program typically awards more than $15 million a year and has given out more than $100 million since 1999, according to the parks department. Its small-grant category tops out at $100,000, the amount Columbia City requested. Cities with fewer than 5,000 residents must put up a match of at least 5 percent.
What Neighbors Told the City
Two residents raised safety concerns about the park at the committee’s September meeting. Katrina Clift said the bark under the play equipment needs to be replenished and that she “hopes that the grant comes through, so we get a new safe playground,” the minutes say. She and Cora Lee Aho both said children push through the arborvitae hedge at Penn Street and Sixth Place and come out where drivers cannot see them. Aho said she has had to slam on her brakes because a child ran through.
Rogers told them the city is looking at changes at that corner, including to the trees, along with off-street parking that includes an accessible space and a new accessible path to the play area. If the hedge is not removed, he said, something else can be done about the hazard.
What Is Not Yet Known
The minutes do not say how much the city has pledged as its match, which pieces of the plan’s list the grant would cover, or when work would start. The Tribune could not obtain the commission’s list of recommended awards before publication and will update this story after Wednesday’s vote.